Reinforcing and securing the Bras de la Plaine water catchment

COUNTRY / PLACE
France

 / Réunion Island

CLIENT
SAPHIR

START DATE :

June 2012

END DATE :

August 2018

Project description

Commissioned in 1971, this hydroelectric structure exhibited recurring issues that led to numerous reinforcements works over the decades. Despite these costly works, carried out under particularly constrained access conditions, the dam and its counter-dam remained in a state of advanced deterioration.   

Following a thorough assessment by SCP, which highlighted the unsuitability of the weir profiles for the river’s hydraulic conditions, SAPHIR initiated a comprehensive program for the renovation and securing of the structure. This €10 million project aims to sustainably restore the hydraulic and structural performance of the Bras de la Plaine intake. 

 

Services provided by SCP: